DAFTAR ANALISA HARGA SATUAN UNTUK PEK. TANAH | ||||||||||
PEKERJAAN | : | GALIAN TANAH | ||||||||
TAHUN ANGGARAN | : | 2010 | ||||||||
6.1 | 1 m3 Galian tanah biasa sedalam 1 meter | |||||||||
NO. | URAIAN | SATUAN | KUANTITAS | HRG. SATUAN | BIAYA SATUAN | |||||
( Rp ) | ( Rp ) | |||||||||
A. | TENAGA KERJA | |||||||||
1. | Pekerja | HO | 0.400 | 35,000.00 | 14,000.00 | |||||
2. | Tukang Gali | HO | - | 50,000.00 | - | |||||
3. | Kepala Tukang | HO | - | - | - | |||||
4. | Mandor | HO | 0.040 | - | - | |||||
JUMLAH A | 14,000.00 | |||||||||
6.4 | 1 m3 Galian tanah keras sedalam 1 meter | |||||||||
NO. | URAIAN | SATUAN | KUANTITAS | HARGA SATUAN | BIAYA SATUAN | |||||
( Rp ) | ( Rp ) | |||||||||
A. | TENAGA KERJA | |||||||||
1. | Pekerja | HO | 0.625 | 35,000.00 | 21,875.00 | |||||
2. | Tukang Gali | HO | - | - | ||||||
3. | Kepala Tukang | HO | - | - | ||||||
4. | Mandor | HO | 0.062 | - | - | |||||
JUMLAH A | 21,875.00 | |||||||||
6.5 | 1 m3 Galian tanah cadas sedalam 1 meter | |||||||||
NO. | URAIAN | SATUAN | KUANTITAS | HARGA SATUAN | BIAYA SATUAN | |||||
( Rp ) | ( Rp ) | |||||||||
A. | TENAGA KERJA | |||||||||
1. | Pekerja | HO | 1.250 | 35,000.00 | 43,750.00 | |||||
2. | Tukang Gali | HO | - | - | ||||||
3. | Kepala Tukang | HO | - | - | ||||||
4. | Mandor | HO | 0.125 | - | - | |||||
JUMLAH A | 43,750.00 | |||||||||
6.6 | 1 m3 Galian tanah lumpur sedalam 1 meter | |||||||||
NO. | URAIAN | SATUAN | KUANTITAS | HARGA SATUAN | BIAYA SATUAN | |||||
( Rp ) | ( Rp ) | |||||||||
A. | TENAGA KERJA | |||||||||
1. | Pekerja | HO | 0.823 | 35,000.00 | 28,805.00 | |||||
2. | Tukang Gali | HO | - | - | ||||||
3. | Kepala Tukang | HO | - | - | ||||||
4. | Mandor | HO | 0.083 | - | - | |||||
JUMLAH A | 28,805.00 | |||||||||
6.7 | 1 m2 Pekerjaan stripping setinggi 1 meter | |||||||||
NO. | URAIAN | SATUAN | KUANTITAS | HARGA SATUAN | BIAYA SATUAN | |||||
( Rp ) | ( Rp ) | |||||||||
A. | TENAGA KERJA | |||||||||
1. | Pekerja | HO | 0.050 | 35,000.00 | 1,750.00 | |||||
2. | Tukang Gali | HO | - | - | ||||||
3. | Kepala Tukang | HO | - | - | ||||||
4. | Mandor | HO | 0.005 | - | - | |||||
JUMLAH A | 1,750.00 | |||||||||
6.9 | 1 m3 Urugan kembali | |||||||||
NO. | URAIAN | SATUAN | KUANTITAS | HARGA SATUAN | BIAYA SATUAN | |||||
( Rp ) | ( Rp ) | |||||||||
A. | TENAGA KERJA | |||||||||
1. | Pekerja | HO | 0.192 | 35,000.00 | 6,720.00 | |||||
2. | Tukang Gali | HO | - | - | ||||||
3. | Kepala Tukang | HO | - | - | ||||||
4. | Mandor | HO | 0.019 | - | - | |||||
JUMLAH A | 6,720.00 | |||||||||
6.10 | 1 m3 Pemadatan tanah | |||||||||
NO. | URAIAN | SATUAN | KUANTITAS | HARGA SATUAN | BIAYA SATUAN | |||||
( Rp ) | ( Rp ) | |||||||||
A. | TENAGA KERJA | |||||||||
1. | Pekerja | HO | 0.500 | 35,000.00 | 17,500.00 | |||||
2. | Tukang Gali | HO | - | - | ||||||
3. | Kepala Tukang | HO | - | - | ||||||
4. | Mandor | HO | 0.050 | - | - | |||||
JUMLAH A | 17,500.00 | |||||||||
6.11 | 1 m3 Urugan pasir | |||||||||
NO. | URAIAN | SATUAN | KUANTITAS | HARGA SATUAN | BIAYA SATUAN | |||||
( Rp ) | ( Rp ) | |||||||||
A. | TENAGA KERJA | |||||||||
1. | Pekerja | HO | 0.300 | 35,000.00 | 10,500.00 | |||||
2. | Tukang Gali | HO | - | - | ||||||
3. | Kepala Tukang | HO | - | - | ||||||
4. | Mandor | HO | 0.010 | - | - | |||||
JUMLAH A | 10,500.00 | |||||||||
B. | BAHAN | |||||||||
1. | Pasir urug | M3 | 1.200 | 75,000.00 | 90000 | |||||
JUMLAH | 90,000.00 | |||||||||
JUMLAH A + B | 100,500.00 | |||||||||
DAFTAR ANALISA HARGA SATUAN UNTUK PEK. PONDASI | ||||||||||
PEKERJAAN | : | PONDASI | ||||||||
TAHUN ANGGARAN | : | ## | ||||||||
6.4 | 1 m3 Pasang pondasi batu kali, 1 Pc : 3 Ps | |||||||||
NO. | URAIAN | SATUAN | KUANTITAS | HARGA SATUAN | BIAYA SATUAN | |||||
( Rp ) | ( Rp ) | |||||||||
A. | TENAGA KERJA | |||||||||
1. | Pekerja | HO | 1.500 | 35,000.00 | 52,500.00 | |||||
2. | Tukang Batu | HO | 0.600 | 50,000.00 | 30,000.00 | |||||
3. | Kepala Tukang | HO | - | |||||||
4. | Mandor | HO | - | |||||||
JUMLAH | 82,500.00 | |||||||||
B. | BAHAN | |||||||||
1. | Batu Kali | M3 | 1.100 | 120,000.00 | 132,000.00 | |||||
2. | Semen Portland | Kg | 202.000 | 1,000.00 | 202,000.00 | |||||
3. | Pasir pasang | M3 | 0.485 | 115,000.00 | 55,775.00 | |||||
JUMLAH | 389,775.00 | |||||||||
JUMLAH A + B | 472,275.00 | |||||||||
6.14 | 1 m3 Pasang pondasi batu kosong / anstamping | |||||||||
NO. | URAIAN | SATUAN | KUANTITAS | HARGA SATUAN | BIAYA SATUAN | |||||
( Rp ) | ( Rp ) | |||||||||
A. | TENAGA KERJA | |||||||||
1. | Pekerja | HO | 0.780 | 35,000.00 | 27,300.00 | |||||
2. | Tukang Batu | HO | 0.390 | 50,000.00 | 19,500.00 | |||||
3. | Kepala Tukang | HO | - | |||||||
4. | Mandor | HO | - | |||||||
JUMLAH | 46,800.00 | |||||||||
B. | BAHAN | |||||||||
1. | Batu Kali | M3 | 1.200 | 120,000.00 | 144,000.00 | |||||
2. | Pasir urug | M3 | 0.300 | 75,000.00 | 22,500.00 | |||||
JUMLAH | 166,500.00 | |||||||||
JUMLAH A + B | 213,300.00 | |||||||||